Meghnaghat 718 MW (net) Combined Cycle Power Plant

 

The Project has been developed on the 35.88 acres land at the Meghnaghat Complex provided by BPDB to the Company on a long-term lease under the Land Lease Agreement. The power generated by the Project has been evacuated through the existing 400 kV network of Power Grid Company of Bangladesh (PGCB). The Company has secured all necessary approvals and permits and maintaining 100% compliance for the project,and will be commencing commercial operation shortly.  

Project Name : Meghnaghat 718 MW (net) Combined Cycle Power Plant
Capacity : Net: 718 MW
Location : Meghnaghat, Boronagar, Sonargaon, Narayanganj
Latitude and Longitude : 23° 36’29” N & 90° 35’ 39” E
Fuel : Natural Gas / RLNG
Configuration : 2 nos GE Gas Turbine, Model No: 9F.04 AGP
: 1 no GE Steam Turbine, Model No D11
: 2 nos Heat Recovery Steam Generator
Power Offtaker : Bangladesh Power Development Board
Gas Supplier : Titas Gas Transmission & Distribution Company Limited
EPC Contractor : Samsung C&T Corporation

 

Project Scheme: